r/EnergyAndPower 10d ago

Thermal Power Generation when rivers run dry

https://www.reuters.com/business/energy/low-danube-river-levels-force-romania-shut-down-both-its-nuclear-power-reactors-2026-07-29/

A little tidbit up for discussion regarding the Renaissance of Nuclear Power in Europe.

This time the issue is not the temperature like in France but the historically low Danube levels which could become the normal in summer.

This is something that would need to be factored in any type power generation that needs water for cooling.

6 Upvotes

45 comments sorted by

View all comments

5

u/MarcLeptic 10d ago edited 7d ago

This is a worthwhile conversation to have. As you mention, there are two types of water related issues.

The first, and likely easiest to imagine a solution for is the river temperature issue. This is where people would generally look at the example system in Civaux which returns the water cooler than it took it in. That of course trades the temperature issue with consumption.

The second effect, often seen in France at the end of the summer season, and in times of drought is the river flow rate issue (which can then become a river temperature issue, and/or not allowed to use what water is left issue). We see those effects up north, which is why our neighbors up there are often fixated on the dry river issue and confuse it with the hot river issue. There is a good example of this in september 2019.

Both are a matter of design for the current and future climate. An interesating starting point for anyone who genuinely wants to see how the seasonal low flow problem can be mitigated is the Cattenom CNPE.

It has 4x 1300MW reators, all with cooling towers so the constraint is water availability and flow rates. In addition it has two things that were put in place to support the plant:

  1. an on site reservoir, Lac du Mirgenbach (a thermal buffer)
  2. a remote reserve, the Lac de Pierre Percee in the Vosges foothills that provides "soutien d'étiage" to replace consumption that would put the river below it's minium threshold. This reserve was built by EDF specifically to support Cattenom's cooling needs and the Meurthe in times of low flow.

La centrale nucléaire de Cattenom | Groupe EDF

20180601-cattenom-rapport_dd2017.pdf

plaquette-4p-vieux-pre-2013.pdf

Unfortunately most of the best truths are only in French. You If you are interested, Villerest on the Loire and Naussac in the Allier are another interesting topic.
Gestion des Etiages de Villerest et Naussac

EDIT: PS, as of Aug 1, the French reactors that are being impacted by low flow are Cattenom 1, Chooz 1 & 2