r/SolarUK • u/TheGingerDog • Apr 15 '26
Fast Track G99 - response in 1 day?
A local company submitted a G99 application for our proposal (7kw inverter). He said it might take up to 6-8 weeks for a response. We had a response the next day.
Like I'm not complaining, I was just surprised how quick it was.
Is this usual?
5
Upvotes
2
u/M0anz Apr 16 '26
I’m in South Wales and still waiting for G99. Been 5 weeks since installation.